x510 Series Installation Guide for Virtual Chassis Stacking

109

Figure 57. Installing an SFP or SFP+ Transceiver

Note

If you are ready to attach the fiber optic cable to the transceiver,
continue with the next step. Otherwise, repeat steps 1 to 4 to install
the remaining SFP or SFP+ transceivers in the line cards.

5. Remove the dust cover from the transceiver, as shown in Figure 58.

Figure 58. Removing the Dust Cover from an SFP or SFP+ Transceiver

6. Verify the position of the handle on the SFP transceiver. If the

transceiver is in a top slot, the handle should be in the upright position,
as shown in Figure 59 on page 110. If the transceiver is in a bottom
slot, the handle should be in the down position.