3 Installing the Air Locker

13

3.4

Checking for Assembly Clearance

IMPORTANT:

Some third member castings will require modification for

correct Air Locker installation. A properly installed

Air Locker will have no less than 2mm [1/16”] between any

part of the differential carrier and the third member casting.

Reassemble the pinion shaft assembly using only 2 bolts finger

tight. (The pinion shaft assembly will be fully assembled later)

Hold the tapered roller bearing cups onto the cones on the carrier.
Carefully insert the carrier assembly into the third member so that

the ring gear is in mesh with the drive pinion.

Using an automotive feeler gauge, check for adequate clearance

between the body of the Air Locker and the third member casting
around the pinion support bearing and behind the flange cap.

If necessary, remove the pinion shaft assembly and grind or file the

third member casting to gain clearance. An example of relief
grinding areas are shown in Figure 6.

Figure 6.