SECTION 2 - PROCEDURES

2-16

– JLG Lift –

3120686

NOTE: Self-locking setscrews used on piston nuts should be

discarded and replaced whenever they are removed.

8.

If applicable, install the setscrew(s) which secure the
piston attaching nut to the diameter groove.

9.

Remove the cylinder rod from the holding fixture.

10.

Place new o-rings and seals in the applicable out-
side diameter grooves of both the piston and the cyl-
inder head.

11.

Position the cylinder barrel in a suitable holding fix-
ture.

EXTREME CARE SHOULD BE TAKEN WHEN INSTALLING THE
CYLINDER ROD, HEAD, AND PISTON. AVOID PULLING THE ROD
OFF-CENTER, WHICH COULD CAUSE DAMAGE TO THE PISTON
AND CYLINDER BARREL SURFACES.

12.

With barrel clamped securely, and while adequately
supporting the rod, insert the piston end into the
barrel cylinder. Ensure that the piston loading o-ring
and seal ring are not damaged or dislodged.

13.

Continue pushing the rod into the barrel until the cyl-
inder head gland can be inserted into the barrel cyl-
inder or, if applicable, until the cylinder head threads
engage the threads of the barrel.

14.

If applicable, secure the cylinder head retainer using
a suitable spanner type wrench in the holes pro-
vided.

15.

After the cylinder has been reassembled, the rod
should be pushed all the way in (fully retracted) prior
to the reinstallation of any holding valve or valves.

16.

If applicable, install the cartridge-type holding valve
and fittings in the rod port block using new o-rings
as applicable.

IF THE CYLINDER IS TO BE TESTED PRIOR TO INSTALLATION ON
THE MACHINE, EXTREME CARE SHOULD BE USED TO INSURE
THAT THE OUTER END OF THE ROD IS SUPPORTED. USE
EITHER A TRAVELING OVERHEAD HOIST, FORKLIFT, OR OTHER
MEANS TO SUPPORT THE OVERHANGING WEIGHT OF THE
EXTENDING ROD.

NOTE: Steps (17) through (20) apply to the telescope cylin-

der.

17.

Elevate the barrel end of the cylinder to a work
bench or other suitable device.

18.

Plug the retract port and supply hydraulic power to
the extend port.

19.

Open the bleeder port plug (TP), venting all trapped
air to atmosphere. Retighten the bleeder port plug.
Disconnect the hydraulic power source and remove
plug from retract port.

20.

An alternative to steps (18) through (20) is to posi-
tion the barrel horizontally in a suitable holding
device, attach a hydraulic power source to both
extend and retract ports, while supporting the cylin-
der rod, cycle the cylinder a minimum of 5 times with

Table 2-2. Cylinder Piston Nut Torque Specifications

Description

Nut Torque Value

(w/Loctite)

Setscrew Torque
Value (w/Loctite)

Axle Extension
Cylinder

400 ft. lb. (542

Nm)

100 in. lb. (11

Nm)

Extend-a-Reach
Cylinder

400 ft. lb. (542

Nm)

100 in. lb. (11

Nm)

Frame Jack
Cylinder

400 ft. lb. (542

Nm)

100 in. lb. (11

Nm)

Level/Slave
Cylinder

200 ft. lb. (271

Nm)

100 in. lb. (11

Nm)

Lift Cylinder

600 ft. lb. (813

Nm)

200 in. lb. (22

Nm)

Master Cylinder

80 ft. lb. (108 Nm)

100 in. lb. (11

Nm)

Steer Cylinder

80 ft. lb. (108 Nm)

100 in. lb. (11

Nm)

Telescope
Cylinder

600 ft. lb. (813

Nm)

200 in. lb. (22

Nm)

Table 2-3. Holding Valve Torque Specifications

Description

Torque Value

Sun - 7/8 hex M20 x 1.5 thds

30-35 ft. lb.

(41-48 Nm)

Sun - 1-1/8 hex 1-14 UNS thds

45-50 ft. lb.

(61-68 Nm)

Sun - 1-1/4 hex M36 x 2 thds

150-160 ft. lb.

(204-217 Nm)

Racine - 1-1/8 hex 1-1/16 - 12 thds

50-55 ft. lb.

(68-75 Nm)

Racine - 1-3/8 hex 1-3/16 - 12 thds

75-80 ft. lb.

(102-109 Nm)

Racine - 1-7/8 hex 1-5/8 - 12 thds

100-110 ft. lb.

(136-149 Nm)