Section 4 - Operation

4-8

3126023

Transporting a Suspended Load

Travel in accordance with the requirements set forth in Section 1 - General Safety
Practices
and Section 5 - Attachments and Hitches.

Important things to remember:

• Ensure the boom is fully retracted.

• Never raise the load more than 300 mm (11.8 in) above ground surface or the

boom more than 45°.

• The combination of side tilt and load could cause the telehandler to tip over.

• Refer to “Use of the Capacity Chart” on page 5-5 for allowable ground conditions

in addition to the appropriate load chart on the machine.

• The guide men and operator must remain in constant communication (verbal or

hand) and be in visual contact with the operator at all times.

• If applicable, refer to “Use of the Capacity Chart” on page 5-5 for additional

proper transporting guidelines.

• Never place the guide men between the suspended load and the telehandler.

• Only transport the load at walking speed (0.4 m/s) or less.

Leveling Procedure

1. Position machine in best location to lift or place load.

2. Apply parking brake and move transmission control lever to NEUTRAL.

3. Move boom so load is no more than 300 mm (11.8 in) above ground surface

and/or boom is raised no more than 45°.

4. Observe level indicator to determine whether machine must be leveled prior to

lifting load.