STARTING UP AND LAGGING DOWN - continued

:


6.

Raise the platform and install the maintenance leg (see “Lift Blocking
Instructions” section).


7.

Lag down the base frame in the holes provided. Lag bolts should be able to
withstand 2000 lbs. minimum upward pull at each corner.


8.

Replace any electrical connections with permanent.


FINAL PREPARATION:



1.

Place the handrails in the platform sockets as shown in Figure 12.


2.

Be sure the maintenance leg is securely in its storage position.


3.

Check oil level of reservoir with the lift in the fully lowered position. Oil should be
1” to 1-1/2” below the top of the reservoir tank. (See the “Maintenance” section
for oil specifications.)


4.

Make sure that all applicable labels are in place in accordance to Figure 1.

WARNING!

All DANGER, WARNING, and CAUTION labels and informational
decals and plates must be intact and in place on the lift. Contact
an Autoquip representative if labels are missing or damaged.


CLEAN UP:


1.

Clean up any spilled oil and debris from the area. A clean installation makes a
good impression and creates a much safer environment!


2.

Touch-up paint is available by request from Autoquip for repair of damaged paint
surfaces.