Finishing installation, Visual inspection, Cleaning – ETC Matrix MkII Rack User Manual

Page 19

Advertising
background image

Finishing Installation

15

6

Section

6

Finishing Installation

Visual inspection

After the supply, load and data terminations are completed, the rack should be checked as follows:

o

Check all terminals and fuses have been tightened, especially the earth bonding
points

o

Tidy all internal cables and add cable ties where needed

o

Remove excess or unwanted wiring

o

Fit the bus bar cover panel

o

Secure all removable panels

o

Remove all temporary protective covers

Cleaning

Before installing any electronics modules, ensure that the rack is free from dust, any building debris.
ETC recommends that the inside of the rack is vacuum cleaned to remove any debris from the wiring
installation process. Special attention should be paid to the multi-pin sockets used to connect to the
processor and modules.

When the rack is clean and ready for use, close and lock the rear door.

Advertising