Initial switch-on, Initial switch−on, 5commissioning – Lenze E82ZAFLC010 User Manual
Page 44

Commissioning
Initial switch−on
EDK82ZAFLC−010 DE/EN/FR 4.0
44
l
H1inbet−statusanzeige
Initial switch−on
)
Note!
ƒ
The standard device is only ready for operation if a HIGH level is applied to
terminal 28 (controller enable via terminal).
– Please note that the controller can be inhibited by various sources. The
sources act like a series connection of switches.
– If the drive does not start even though the controller has been enabled
via terminal 28, check whether the controller has been inhibited by
another source. Another source could be the
s key on the keypad.
ƒ
Please note the different status information for code C0068 compared to
software version "0.1" (see the following table).
Bit
Function
Description
8
RFR (controller enable)
0: no controller enable
1: controller enable
11
IMP (pulse inhibit)
0: pulses for power sections inhibited
1: pulses for power sections enabled
15
TRIP (fault)
0: no fault
1: fault exists