How to connect the filter:
1. De−energise the control cabinet and fuse it against re−energisation.
2. Wait for at least 3 minutes before checking the standard device for isolation from

supply.

3. Wire the filter input cables and the filter output cables according to the connection

plan.
– Observe tightening torque.

4. Wire the DC−bus cables (+UG/−UG) according to the connection plan.

– The terminals +UG und −UG must be connected using the same cable cross−section

as in the motor cable.

– Observe tightening torque.

Only for types with thermal contact:
5. Wire the terminals of the thermal contact

3.

– Integrate the thermal contact into the monitoring system so that the mains

supply is switched off when the filter is overheated.

– NC contact, switching capacity: 250 V AC / 1.6 A
– Connect the twisted cables.
– Observe tightening torque.

)

Note!

When commissioning, please observe that operation is only permissible

ƒ

with V/f or V/f

2

characteristic control

ƒ

at a switching frequency of 4 ... 16 kHz

Ensure that the automatic switching frequency reduction is deactivated (see
documentation of the standard device). The filter will overheat at a switching
frequency of <4 kHz.