A2.0 installation procedure – MTS Criterion 60 - Installation and Commissioning Plan User Manual
Page 6

Installation and Commissioning Plan
Criterion
TM
Series 60 5
A2.0 INSTALLATION PROCEDURE
The system will be installed by an FSE. Depending on the system configuration,
the following activities will be performed:
Item Description
Performed
On Site
A2.1
Verify that all components purchased are present
according to the purchase contract and packing list.
A2.2
Remove packaging on the load unit (for example
mounting clamps and oilpaper).
A2.3 Install
the
cover
boards
A2.4
Attach all required cables between controller and load
unit.
-
Transducers.
-
Computer.
A2.5
Attach all hoses between load unit and Integrated
Operations Platform.
A2.6
Fill hydraulic oil to the reservoir.
A2.7
Install purchased grips and fixtures as required
(including any auxiliary power supplies for grips.)
A2.8
Install purchased environmental simulation products.
(For example, safety enclosure, steps and furnace)