page 24 — gaC9.7HZ 60 HZ geNeRaTOR• OpeRaTiON aNd paRTs maNual — Rev. #2 (03/31/10)

OperatiOn/sHutdOwn

16. The L14-30R receptacle is a dual voltage receptacle

(120-240 volts). Reference Figures 23 and 24 to verify

voltages at this receptacle.

Figure 23. 120/240V Receptacle (120V)

Figure 24. 120/240V Receptacle (240V)

17. Connecting of loads (power tools, lighting ect.) to the

generator receptacles can now be done.

NOTICE

When using a combination of dual receptacles, total

load should not exceed the rated capacity of the

generator.

stopping the engine (Normal shutdown)

1. Place

main circuit breaker (Figure 25) in the OFF

position.

Figure 25. Main Circuit Breaker (OFF)

2. Place

GFCI and AUX. circuit breakers (Figure 26) in

the

OFF positing.

Figure 26. GFCI/AUX. Circuit Breakers (OFF)

3. Place idle control switch (Figure 27) in the

OFF position.

Figure 27. Idle Control switch (OFF)

4. Let engine run at idle with no load for 2-3 minutes.
5. To shut-down the engine, place the generator's

operation switch (Figure 28) in the

OFF position).

Figure 28. Operation Switch (OFF)

6. Remove all loads from the generator.

emergency shutdown

1. Place operation switch (Figure 28) in the

OFF position.