10 • 35-3000RK-10 PPM Hexane Sample Draw Detector

Installation

This section describes procedures to mount the sample draw detector in the monitoring
environment and wire the sample draw detector to a controller.

Mounting the Sample Draw Detector

1.

Select the mounting site. Consider the following when you select the mounting site.

Is there enough room to open the housing door and make wiring connections at
the bottom of the housing and tubing connections at the right of the housing?

Make sure there is sufficient room to perform start-up, maintenance, and
calibration procedures.

Are the flowmeter and status LEDs visible?

Figure 3: Outline & Mounting Dimensions

2.

Close and latch the housing door.

6.5 in.

4.0 in.

Note: The housing is 4.25 in. deep.

8.5

in.

9.3

in.

8.9

in.

3/4 in. conduit hub

(total of 2 hubs)

7.3 in.