Installation – RKI Instruments 65-2397RK User Manual
Page 9

65-2397RK CO
2
Transmitter • 5
Installation
This section describes procedures to mount the CO
2
transmitter in the monitoring
environment and wire the transmitter to a controller.
Mounting the CO
2
Transmitter
1.
Select a mounting site that is representative of the monitoring environment. Consider
the following when you select the mounting site.
•
Select a site where the transmitter is not likely to be bumped or disturbed. Make
sure there is sufficient room to perform start-up, maintenance, and calibration
procedures.
•
Mount the transmitter at least six feet from the floor to minimize the possibility of
someone breathing on the unit. The exhaled CO
2
may cause an alarm.
Figure 3: Mounting the CO
2
Transmitter
2.
At the monitoring site you select, hang or mount the junction box with the detector
facing down (see Figure 3).
Rubber
Spacers,
3X
3.10
.75
.38
3.65
3/4 NPT
Female
1 1/2-20 Thread for
Calibration Cup
J-Box
IR CO2
Detector
6.80 MAX