2.

INSTALLATION IN COMMERCIAL AIRCRAFT HANGARS

Luminous (high intensity) radiant tube heaters are suitable for use in aircraft hangars when in-
stalled in accordance with the latest edition of the Standard for Aircraft Hangars, ANSI/NFPA
No 409 in the USA, or the Canadian Natural Gas and Propane Installation Code, B149.1.

A. A minimum clearance of 10 ft (3 m) above either the highest fuel storage compartment or

the highest engine enclosure of the highest aircraft which may occupy the hangar. The
clearance to the bottom of the heater shall be measured from the upper surface of either
the fuel storage compartment or the engine enclosure, whichever is higher from the floor.

B. A minimum clearance of 8 ft (2.4 m) must be maintained from the bottom of the heater to

the floor in other sections of the aircraft hangar, such as offices and shops, which communi-
cate with areas for servicing or storage. Refer to Table 1 for proper mounting clearances to
combustibles.

C. Heaters must be located so as to be protected from damage by aircraft and other objects,

such as cranes and movable scaffolding.

D.Heaters must be located so as to be accessible for servicing and adjustment.

3. INSTALLATION IN COMMERCIAL GARAGES AND PARKING STRUCTURES

Luminous (high intensity) radiant heaters are suitable for use in commercial garages when in-

stalled in accordance with the latest edition of the Standard for Parking Structures, ANSI/NFPA

88A, or the Standard for Repair Garages, ANSI/NFPA No. 88B, or the Canadian Natural Gas

and Propane Installation Code, B149.1.

An overhead heater shall be located to maintain the minimum

distance to combustibles, as shown on the heater rating plate,

from the heater to any vehicles parked below the heater.

Overhead heaters shall be installed at least 8 ft (2.4 m) above the floor.

4.

INSTALLATIONS OTHER THAN SPACE HEATING

Use for process or other applications that are not space heating will void the C.S.A. certification

and product warranty. Process application requires field inspection and/or certification by local

authorities having jurisdiction. Process application design should be provided by local experi-

enced process design experts.

5.

PRE INSTALLATION SURVEY

It is recommended that a full heating design including heat loss calculation be conducted on

the structure or area to be heated. Heater sizing and placement must consider available

mounting height, sources of greatest heat loss, and obstructions on the site. The certified clear-

WARNING