Schwank SEB(U) User Manual

Page 22

Advertising
background image

SP-MSEB-BX-10A

SEB Manual

RD: JUNE 2004

RL: 10

KH

Page 20

Page 18

17. LIGHTING INSTRUCTIONS

Refer to the lighting instructions on the inside
cover of the burner housing. Again, if the
unit goes off on safety, main power to the unit
must be manually interrupted for a 30 second
reset period before the heater can be restarted.
NOTE:
On initial installation, the unit may
lock out on safety owing to the length
of time required to bleed air from the
gas piping system

.

Rotate gas valve knob to ON position.

Set Thermostat to the desired setting.

Turn Power ON to heater.

This should start the Blower, sending the
DSI Control into its pre-purge cycle, then
into ignition, and light off.

If heater fails to light, shut down heater
and wait 5 minutes before relighting it

To shut down the heater just reverse the
previous steps..

18. RECOMMENDED MAINTENANCE

THE SCHWANK TUBE HEATER BURNER IS COMPLETELY FACTORY ASSEM-
BLED AND TESTED. ANY ALTERATION VOIDS THE CSA CERTIFICATION AND
MANUFACTURERS WARRANTY. FOR ADDITIONAL INFORMATION, CONTACT
YOUR LOCAL DISTRIBUTOR OR SCHWANK LTD.

Each 10’ section of the SEBU Series Heater is hung by 4 chains, supporting 2 brackets, 2 tubes
and one reflector. The heater may be hung at an angle up to 45 providing the Burner Tube is in
the lower position and the flue end in the upper position.

LIGHTING SEQUENCE:

1. Inspect the venting system each heating

season and repair or replace worn parts as
required.

2. Check the inlet air opening and the

blower periodically, cleaning off any lint
or foreign matter, as it is important that
the flow of combustion and ventilation air

must not be obstructed. In addition we
recommend the entire system be checked
once a year by a qualified service techni-

cian.

3. Lubricate Blower motor, by adding several

drops of oil to oil ports located on the left
hand side of the motor.

Advertising