Installation
Instructions for energizing loads before commissioning
Figure 5 - Rear view of Automatic Bypass Switch board
If the MegaDySC system must 
be installed and put into 
maintenance bypass mode 
before commissioning, the 
installers should put the 
system enclosures in place as 
described on 
, then
feed the loose ends of inter-
cabinet cables from the 
switchboard into the 
MegaDySC cabinet:
1.
Route the INPUT 
power cables (labeled 
L1, L2, L3) through the 
top bushing in the 
right-side wall of the 
switchboard, labeled 
“Input to DySC” 
2.
Route the OUTPUT 
power cables (X1, X2, 
X3) and Ground cable through the bottom bushing labeled “Output from 
DySC”
3.
Route the control cable harness from the lower front switchboard pan into 
the MegaDySC section through the matching holes in the lower front side 
panels. Install the 3.5” snap-in grommet so that it protrudes into the 
MegaDySC cabinet before routing the harness. Plug the harness header 
into connector TB5 on the MegaDySC floor.
4.
Lockout circuit breakers CBI and CBO in the Automatic Bypass 
Switchboard.
5.
Install utility input and load output conductors.
6.
Energize the switchboard. 
The MegaDySC touch screen display will be active only if the control 
harness has been plugged in on the MegaDySC side. If the screen is active 
then 120VAC is present at several points within the MegaDySC enclosure.
7.
Push the green CLOSE CBB button to energize loads.
The remaining interconnections and commissioning must be completed 
by factory-trained technicians.
WARNING:  120VAC is present at several pins of the harness header when the 
switchboard is energized.