Wiring
It is recommended that conduit be installed onto the ¾” NPT connection on the electronics housing. A seal drain fitting
should be used to prevent moisture from entering the switch. All wiring, conduit, and electrical fittings must conform to
local electrical codes for the location selected. If the switch is to be used in a Hazardous Area, the applicable codes of the
National Electrical Code must be followed as well.
























1. Connect power wiring

a. AC – Hot (L2), Neutral (L2), and Ground (G)
b. DC – Positive (L1), Negative (G)

2. Connect relay wiring (see diagram)
3. Connect Manual Self-Test terminals to a remote pushbutton (maximum distance 30 feet).
4. Adjust failsafe jumper

a. HLFS – top (2) pins
b. LLFS – bottom (2) pins



The following table shows the relay condition for each switch state:

Relay Terminals

Media

Level

Fail Safe

Setting

Relay

Condition

NC to C

NO to C

HLFS

De-Energized

Closed

Open

Above

Setpoint

LLFS

Energized

Open

Closed

HLFS

Energized

Open

Closed

Below

Setpoint

LLFS

De-Energized

Closed

Open



+

G

L2

L1

NC

C

NO

NC

C

NO

-

Jumper
High Level Failsafe
(HLFS)

Low Level Failsafe
(LLFS)

}

115Vac or 230Vac

50/60 Hz

}

12 or 24Vdc

+

-

{

Molex Conn. &

Coaxial Cable

To Sensor

Manual Self-Test

Maximum Wiring