Hoisting via Stacking Frame Handles


WARNING

When hoisting via the stacking frame handles it is mandatory to use at least

four rigging points (two opposite sides). Straps must be placed on either side

of designated label on the stacking frame handles.

1. If the projector is inverted retract the adjustable feet to prevent the hoisting

hardware from becoming snagged.

WARNING

Always use at least two safety cables when hoisting

and attach them to the two eyebolts on the stacking frame.

2. Attach a safety cable to at least of the eyebolts

mounted on the bottom of the stacking frame.

3. Secure the rigging components to the

appropriate rigging points. Refer to the
designated labels on the stacking frame handles
for rigging positions.

4. It is mandatory to use four rigging points. Ensure

the straps, clamps or cabling meet the adequate
load capacity for the total projector(s) weight.
DO NOT join the rigging straps or cables to a
common point — keep separated.

Refer to Figure 4.

Figure 4. Four Rigging Points