EFCO S5500 SSG User Manual
Page 12
Advertising

EFCO CORPORATION 6/2012
PART NO. Y554
Series 5500 Silicone Structural Glazed Curtain Wall Installation Instructions
Section II: Frame Unit Assembly & Frame Sealing
SSG INTERMEDIATE HORIZONTALS
AT SSG REVEAL JAMBS
SSG INTERMEDIATE HORIZONTALS
AT SSG INTERMEDIATE VERTICAL
Apply H10Z Gasket to
each end of the Hori-
zontal. Trim excess
gasket after assembly.
OR
Apply a generous bead
of sealant to the ends
of the horizontal mul-
lions to a minimum of
1” back from the face
of the horizontal glaz-
ing pocket.
Apply H10Z Gasket to
each end of the Hori-
zontal. Trim excess
gasket after assembly.
OR
Apply a generous bead
of sealant to the ends
of the horizontal mul-
lions to a minimum of
1” back from the face
of the horizontal glaz-
ing pocket.
Advertising