Series 5500 Silicone Structural Glazed Curtain Wall Installation Instructions
Section III: Typical Anchorage Methods
STEP #2 INSTALL FRAME COMPONENTS
A. Set the first frame into the opening using dead load shims to level the frame, and make all
necessary adjustments to properly locate the frame to established benchmarks.
B. After the frame is plumb and all adjustments have been made, match drill through the
holes in the head and sill into the surrounding substrate, and apply the anchor bolts. An-
chor bolt size, type, quantity, and location vary. Refer to the approved shop drawings for
more information.