Install-adjacent-frame – Oldcastle BuildingEnvelope Signature Series Unit Wall User Manual

Page 16

Advertising
background image

July 2013

15-Install-Adjacent-Frame

1-866-Oldcastle (653-2278) www.oldcastlebe.com

SIGNATURE SERIES UNIT WALL INSTALLATION MANUAL

INSTALL GROUND FLOOR FRAMES

2. INSTALL ADJACENT FRAMES AT GROUND FLOOR

Just prior to installing the next frame, apply sealant at the bottom of the first frame up vertical air seal
gasket GP-50001 for approximately 4" long above horizontal air seal gasket. Connect the vertical seal

with the horizontal seal which was previously applied on top of the starter sill. Do not allow sealant to

skin before installing next frame.

Apply 4" long sealant
at the bottom of the mullion
along vertical air seal gasket

Connect vertical seal
with horizontal seal

Install the next frame by lifting the frame up to clear the starter sill. Move the next frame to the left to

engage the outer mullion hooks; then rotate the next frame towards building to snap inner hooks;
once snapped, slide the next frame down to engage horizontal air seal at stack joint.

Again use the adjustment bolt to level the frame. Check and ensure vertical air seal gasket GP-50001

has not slid down in the gasket raceway in mullion.

Repeat in the same method for installing the rest of the frames at ground floor.

3"

- 6

"

4"

Advertising