Example of a Double Section 28' x 72' Home

WIND ZONE I for Double Section Homes (High Pier Sets)

Using Vector Dynamics Foundation Systems

Soil Bearing Capacity: 1,000 PSF Minimum

Anchors Required:

30" with 2-4" helix anchors (#59095), 12" Stabilizer Plates (#59292)

& 1-1/4" frame tie with connector

Home Length

Vector Systems

Anchors Required

Longitudinal

Required

Per Side

System (LSD)*

0 to 48'

2

2

2 (4 Struts)

49' to 71'

3

3

2 (4 Struts)

72' to 84'

4

4

2 (4 Struts)

85' to 90'

5

5

2 (4 Struts)

NOTES:
Pier height is measured from top of the Vector Pad to the
bottom of the I-beam.

Vector Systems should be spaced as symmetrically as
possible along the length of the home. Pier spacing must
be consistent with home manufacturers instruction and/or
state requirements.

* One Longitudinal Vector System is made up of 2

struts, which can be used separately.

Vector System

LSD

LSD

Vector System

Anchors &

Stabilizer Plates

Unit Width

See below

chart

I-Beam

Spacing

45˚

Min.

156”

156”

156”

164”

164”

164”

180” Min

180” Min

180” Min

140” Min

140” Min

140” Min

82.5”

95.5”

99.5”

82.5”

95.5”

99.5”

82.5”

95.5”

99.5”

82.5”

95.5”

99.5”

88”

70”

65”

98”

81”

76”

119”

101”

96”

66”

48”

43”

86”

69”

64”

96”

80”

74”

117”

100”

95”

64”

47”

42”

85”

68”

63”

95”

78.5”

73”

115”

99”

94”

64”

47”

42”

Wall Height & Trib

Max. Pier Height

7.0’

Trib=19’

7.5’

Trib=18’

8.0’

Trib=17’

Unit

Width

W

I-Beam

Spacing

IBS

Wind Zone I

Advertising
This manual is related to the following products: