Long U-Bolts

Page 9

4/3/2013

Set-Up Instructions for

Vector System #59018

1. Set Vector Pads
Clear all vegetation where pads will rest. Place a long
U-bolt in pad as shown. Press or hammer pad into the
ground.

2. Set Block or piers on pads.
Center foundation blocks or piers on pads. Place
pre-cut center compression member between blocks,
resting on pads, centers between U-bolts as shown.

3. Outside Tension Bracket
Attach outside tension bracket as shown to outside
of pads.

4. Inside brackets & straps
Attach the inside tie brackets to the U-bolts over the
compression member. Attach a strap w/hook or swivel
strap w/nut & bolt. Place other end of the strap over
opposite I-beam & down to outside tension bracket.
Cut strap 12 - 15 inches past bracket. Attach strap
& slotted bolt in bracket. Tighten strap until tight with
4-5 wraps around bolt. Repeat with opposite strap.