Phase iii, Installation - piping – TriangleTube TR Series User Manual

Page 12

Advertising
background image

Phase III

®

9

Cold Water

Inlet

6

1

Recirculating

Loop

2

3

4

1

5

5

1

10

9

12" min.

Heat Trap

Loop

12" min.

Heat Trap

Loop

11

Cold Water

Inlet

6

1

Recirculating

Loop

2

11

3

12" min.

Heat Trap

Loop

12" min.

Heat Trap

Loop

4

1

5

5

1

10

9

Standard Installation
Domestic Piping with Recirculation
TR Series

1. Shut-off valves
2. Recirculation circulator
3. Flow check valve
4. T&P relief valve
5. Unions

6. Backflow preventer or pressure reducing valve(*)
9. Drain valve
10. Thermal expansion tank (potable)
11. Dip Tube - Recirculation per Chart 1

(*) Optional devices may be required by local codes.

Standard Installation
Domestic Piping with Recirculation
SMART Series

Figure 2

Installation - Piping

Advertising
This manual is related to the following products: