Dvbr series direct vent gas fireplace, Fp1184 typical roof/ceiling support apps, Vertical through-the-roof installation – Vermont Casting DVBR36 User Manual

Page 20

Advertising
background image

20

DVBR Series Direct Vent Gas Fireplace

20000584

1
2
3
4

1
2
3
4

1 + 2 + 3 + 4 = 270°

FP1179

Fig. 42 Maximum elbow usage.

FP1184
Typical roof/ceiling
support apps.

FP1184

Typical Roof

Support Ap-

plication

Typical Ceiling Sup-

port Application

Fig. 44 Venting supports.

Joist

Attic Insulation Shield

Ceiling
Installation

Upper Floor

11”

Firestop
Spacer

Nails (4)

Fig. 43 Place firestop spacer(s) and secure.

VR404

11”

5. Place firestop(s) #7DVFS into position and secure.

(Fig. 43)

6. Install roof support (Fig. 44) and roof flashing

making sure upper flange of flashing is below the
shingles. (Fig. 46)

7. Install appropriate pipe sections until above the

flashing. (Fig. 46)

8. Install storm collar and seal around the pipe.
9. Add additional vent lengths for proper height.
10. Apply high temperature sealant to 4” and 7” collars

of vent termination and install.

If there is a room above ceiling level, firestop spacers
must be installed on both the bottom and the top side
of the ceiling joists. If an attic is above ceiling level
a 7DVAIS (Attic Insulation Shield) must be installed.
The enlarged ends of the vent section always face
downward.

Vertical Through-the-Roof Installation

Max. Height 40’ (12.2m)

Min. Height 8’ (2.4m)

Max. 10’ (3m)

FP1183

Max. Height

40’ (12.2m)

Min. Height 8’

(2.4m)

Max. 10’ (3m)

Fig. 41 Support straps for horizontal runs.

1. Locate your fireplace.
2. Plumb to center of the (4”) 90° transition elbow

(7DVRT90) from ceiling above and mark position.

3. Cut opening equal to 9³⁄₈" x 9³⁄₈" (240 x 240 mm).
4. Proceed to plumb for additional openings through

the roof. In all cases, the opening must provide a
minimum of 1” (25 mm) clearance to the vent pipe,
i.e., the hole must be a minimum of 9³⁄₈" x 9³⁄₈" (240
x 240 mm).