With the engine running smoothly, check the no load

voltage and frequency at wire #  and # 4 (L2 and

L6 in the ASCO ATS) on the generator terminal block

in the ATS. The voltage should be 240 volts plus or

minus nominal. The frequency should be between

6.5 to 62 hertz (Hz). The voltage should also be

checked between the hot terminals (L2 and L6) and

the neutral to be certain of a balanced voltage output

and a solid neutral connection. The voltage should

be about on half of the line to line voltage.

** NOTICE **

If for any reason during the check out procedures

the voltage and frequency are not correct, move the

toggle switch to the “STOP” position and correct the

trouble before proceeding.

After verifying the voltage and frequency are cor-

rect, move the right hand toggle switch to the AUTO

position. The unit should shut off with no time delay.

The right hand toggle switch must be left in the

AUTO position for proper operation of the gen-

erator. If you leave it in the RUN position the fuel

solenoid will remain open and it will not shutdown

properly after the next exercise period.

Transfer Switch & Engine Generator

This procedure checks the electrical operation of

the automatic transfer switch. If the actual operation

does not follow this procedure, consult the trou-

blshooting section in the transfer switch manual.

. Move the left hand toggle switch from the OFF

position to the ON position. The alarm light should

go out. The unit is now ready to be operated from

the Automatic Transfer Switch.

******************

***** WARNING *****

******************

PERSONAL INJURY HAZARD - Install front cover

in transfer switch before operation. An electrical sys-

tem fault could cause a flash and severe personal

injury.

2. Turn on the preferred source (utility) circuit

breaker. The utility source acceptable light should

now come on as well as the transfer switch on utility

light. If these lights fail to come on recheck your

incoming power to insure you have 240 volts nomi-

nal. If not, troubleshoot your utility source before

continuing.

3. Turn on the altenate source (generator) curcuit

breaker.

There are two ways to test your transfer switch

operation: WITHOUT a load transfer or WITH a

load transfer.

WITHOUT load transfer (normal exercise)

. Press and release the

Push to Test button.

The generator set should start immediately. About

5 seconds the generator (alternate source) accept-

able light comes on and stays on.

2. The generator set runs for 20 minutes. The

Transfer Switch does not transfer the load to the

generator set. The

Transfer Switch on utility (pre-