With the engine running smoothly, check the no load

voltage and frequency at wire #  and # 4 (L2 and

L6 in the ASCO ATS) on the generator terminal block

in the ATS. The voltage should be 240 volts plus or

minus nominal. The frequency should be between

6.5 to 62 hertz (Hz). The voltage should also be

checked between the hot terminals (L2 and L6) and

the neutral to be certain of a balanced voltage output

and a solid neutral connection. The voltage should

be about one half of the line to line voltage.

** NOTICE **

If for any reason during the check out procedures

the voltage and frequency are not correct, move

the toggle switch to the “

STOP” position and correct

the trouble before proceeding.

SEE PAGE 24 FOR

PICTORIAL INSTRUCTIONS FOR SETTING THE

FREQUENCY.

After verifying the voltage and frequency are cor-

rect, move the right hand toggle switch to the

AUTO

position. The unit should shut off with no time delay.

The right hand toggle switch must be left in the

AUTO position for proper operation of the gen-

erator. If you leave it in the RUN position, the fuel

solenoid will remain open and it will not shutdown

properly after the next exercise period.

Transfer Switch & Engine Generator

This procedure checks the electrical operation of

the automatic transfer switch. If the actual operation

does not follow this procedure, consult the trouble-

shooting section in the transfer switch manual.

. Move the left hand toggle switch from the

OFF

position to the

ON position. The alarm light should

go out. The unit is now ready to be operated from

the Automatic Transfer Switch.

INITIAL START UP

******************

***** WARNING *****

******************

DO NOT jump start these generator sets. Starting

these units on a low battery by jump starting them

will cause damage to the engine control module.

Use the following checklist to verify correct in-

stallation before starting the engine:

Engine oil. Check level & fill as required with

proper grade/quantity. Refer to engine owners

manual for proper levels and types.

Unit mounting base properly bolted down.

Clearance for service and maintenance on all

sides.

Proper fuel line material and size.

All fuel line connections tight.

Fuel line protected and a moisture trap in

stalled (may be required for NG).

LP/NG pressure OK. 4-6 oz. (7- in. WC).

Battery connections clean and tight.

Battery fully charged.

All AC and DC wiring installed and properly

protected.

After completing the above checklist, the generator

set is ready for the initial start-up test.

START UP PROCEDURE

Engine Generator Set only

Move the left hand toggle switch from

OFF to the

ON position. The alarm light should go out. Next

move the right hand toggle switch from the

AUTO to

the

RUN position. You should hear the fuel solenoid

engage at this time. Next lift the toggle switch to the

START position and hold. The engine starter should

engage and the engine will start. As soon as the

engine starts, release the toggle switch and it will

return to the

RUN position. If the engine does not

start after 5 seconds, release the switch and let the

starter rest for 5 seconds and re-attempt to start. If

the unit still will not start, consult the troubleshooting

guide in the back of this manual.