Commission Check List

Commissioning Check List

G

ENERAL

†

All equipment ordered by the customer is installed.

†

The unit is level and secure.

†

The mains and control wiring are complete and the circuit breaker and GPO are turned ON.

†

All Controller functions for the appliance operate.

†

All electrical or gas connections are to manufacturers specifications and the relevant electrical
or gas standards and codes.

U

NIT

D

UCTED

H

EATING

†

Electrical polarity of the power outlet is correct.

†

Heater is installed away from sources of dust and fumes (ie. pool chlorine/petrol etc).

†

Gas leaks checked for, none present.

†

Flue outlet pipe complies with limits given / code and is sealed waterproof.

†

Combustion air meets requirements (internal, under floor).

†

Fan speed set is correct.

†

Burner pressure is correct.

†

Mounting pad/platform complies with requirements / codes.

D

UCTWORK

†

All ductwork is completed to plan, correctly supported and airtight, with no bend less than 1.5 x
the ductwork diameter.

†

Air distribution checked, dampers are adjusted and all outlets correctly adjusted and wiped
clean.

†

All roof penetrations are fully sealed and watertight.

†

Man-hole cover replaced.

S

ITE

†

All rubbish has been removed from inside and on the roof.

C

USTOMER

H

AND

O

VER

†

The operation of the Thermostat Wall Control.

†

Operation of zones (where fitted) and air outlets.

†

Maintenance & service requirements.