Multiple boiler guide – Dunkirk Helix VLT Vertical Laser Tube, Wall Hung Modulating Condensing Boiler User Manual

Page 3

Advertising
background image

3

2 - Setting Boiler Address

Argus Link Connection And Power Switch S4:

• All boilers must be connected in parallel to Argus Link terminals on low voltage terminal block.
• Maximum wire length is 100' (30m) for 22 gauge, 150' (45m) for 18 gauge.
• Maintain polarity of wires between each boiler.
• Managing boiler control provides power for communication.
• Managing boiler S4 switch has to be in ON position (away from S4 marking).
• All dependent boiler S4 controls must be in OFF position (slider towards from S4 marking).

MULTIPLE BOILER GUIDE

NOTICE

S4 switch is shipped in ON position from

manufacturer. Turn OFF on all dependent boilers.

S4 Switch

ON

OFF

Figure 2 - Control Module S4 Switch

Advertising