Installation, 7 boiler fixing 7.1 hanging bracket fixing, 2 boiler hanging – Glow-worm Ultracom hxi User Manual
Page 19

0020107233_00 - 06/11 - Glow-worm
INSTALLATION
- 19 -
Diagram 7.1
Diagram 7.2
13506
13503
7 boiler fixing
7.1 Hanging bracket fixing
Reposition the wall template over the flue hole and mark
the position of the fixing holes for the hanging bracket, see
diagram 7.1.
Mark and drill the fixing holes and secure the hanging bracket
which is supplied in the polystyrene base pack.
noTe: Due to the varied site conditions we do not supply
fixings and advise that the installer should supply those which
are suitable.
7.2 boiler Hanging
IMPoRTanT: With regards to the Manual Handling
Operations, 1992 Regulations, the following lift operation
exceeds the recommended weight for a one man lift, refer to
section 15 Manual Handling.
Lifting the boiler into position, lean the top of the boiler slightly
to the wall and position just above the hanging bracket. Lower
the boiler slowly and engage onto the hanging bracket, see
diagram 7.2.
Remove the polystyrene base support.