NIBCO Circuit Balancing Valve 1710 User Manual

Installation and operation instructions for nibco, Circuit balancing valves (model t/s-1710), Installation, operation & maintenance instructions

Advertising
background image

INSTALLATION, OPERATION & MAINTENANCE INSTRUCTIONS

CAUTION: Only qualified personnel should undertake the procedures outlined in this document.
NIBCO INC., its agents, representatives and employees assumes no liability for the use of these
procedures. These procedures are offered as suggestions only.

NIBCO Technical Services • Phone: 1.888.446.4224 • Fax: 1.888.336.4224

1

N I B C O I N C .

W O R L D H E A D Q U A R T E R S

1 5 1 6 M I D D L E B U R Y S T.

E L K H A R T, I N 4 6 5 1 6 - 4 7 4 0

U S A

P H O N E : 5 7 4 . 2 9 5 . 3 0 0 0

F A X : 5 7 4 . 2 9 5 . 3 3 0 7

W E B : w w w . n i b c o . c o m

Review Date: 01/18/2012

Original Date: NA

Installation and Operation Instructions for

NIBCO

®

Circuit Balancing Valves

(Model T/S-1710)

PRESSURE/TEMPERATURE RATING

The Figure 1710 is suitable for 290 psi pressure rating. It must be installed in a piping system,
where the normal pressure does not exceed this rating. The maximum temperature is restricted
to 250°F.

SITING

Conventionally, valves and commissioning sets are installed in horizontal pipework. This is,
however, not a constraint and they may be mounted in vertical or inclined pipework, inverted or
rotated to clear walls, ceilings and other restrictions.

INSTALLATION


Unpack the valve and check that the bores are clean and free from foreign material. Also check
that the adjoining pipework is clean and free from debris and burrs.

Confirm that the pipe threading length is correct to avoid excessive penetration of the pipe into
the valve which may otherwise cause damage.

Sealing compound may be used but excessive use of hemp type materials should be avoided
which increases the thread interference and may cause overstressing of the body ends.

Advertising