2.2. Preparing the setup

General
Check the acoustical and mechanical setup using ArrayCalc and

prepare enough printouts for each array.

The plan enables the riggers to set up the suspension points, the

securing points and the chain hoists.
When on site first:

Clear the working areas and ensure there is enough space to

set up and lift the array.

Check that the hoists are exactly in the specified position.

Ensure the chains are not twisted.

Prepare the cables and link cables according to the number of

amplifier channels and cabinets used.

Inspections before setup
Before setup carry out a visual inspection of all system components

for faults. This also includes the loudspeaker and in particular the

rigging parts of the cabinets (Front and Splay/Rear links).

Damaged components must be withdrawn from use immediately.

Please follow the instructions given in Þ Chapter 3. "Care and

maintenance / Disposal" on page 10.

2.3. Order of assembly
Due to the compact size of the V-Series TOP cabinets and the

maximum number of four cabinets that can be flown, the assembly

may be carried out either suspended or on the ground. The

following description refers to the suspended assembly.

1. Prepare the first cabinet
1. At the front release both Locking pins and slide out the Front

link.

2. Insert and lock one Locking pin to fix the link in place.

3. On the rear release both Locking pins and fold out the Splay

link.