De e f f, Electrical connection, Basic settings – Flowserve NRS 1-51 User Manual
Page 16
6
d
d
e
e
f
f
Fig. 8
Fig. 9
Electrical Connection
– continued –
Schematic representations of arrangements
Key
Steam boiler plants according to TRD 604, EN 12952-07 / EN 12953-06, 72 h operation
Fig. 8
Combination consisting of level electrode NRG ...-5 and level switch NRS -5 as high water level
alarm. Functional safety IEC 6508, SIL 3.
Further applications in accordance with national sets of regulations
Fig. 9
Combination consisting of level electrode NRG ...-5 and level switch NRS -5 as high water level
alarm. The level switch opens two separate control circuits. Functional safety IEC 6508, SIL 3.
d
Level electrode(s) NRG ...-5
e
Level switch NRS -5
f
Control circuit
Basic Settings
Factory setting
Level Switch NRS 1-51
The level switch features the following factory set default values:
n
De-energizing delay: 3 sec.