Attention

■

Only qualified welders certified e. g. according to DIN EN 287 may weld the
steam trap into pressurized lines.

■

Do not insulate trap.

Installation

– continued –

Heat treatment of welds

A subsequent heat treatment of the welds is not required.

The flanged connections of the UBK 46 must be permanently bolted, ensuring tight shut-off. If
necessary raise or lower the condensate discharge temperature. For more information refer to section
“Adjust discharge temperature” on the following page.