3 Initial Setup and Start
Installation Guide
STP60-10-IA-xx-10
35
Figure 3.6 LCS tool - List of connected inverters
5. Select the desired country from the list of options
available for the inverters in the network. See figure
3.7.
6. Select the desired grid code from the list of options
available for the selected country. If needed, load a
customer-specific grid code by clicking the "Load"
button. See figure 3.7. The "Create" button is inactive
and cannot be used.
Figure 3.7 LCS tool - Select country and grid code
7. The LCS tool prompts for a confirmation of the selected
country and grid code. See figure 3.8. Incorrect
configuration can be changed using the "Back" button
and changing the settings in the previous windows.