Installing Front Ethernet Module
To install the front Ethernet module, take off the front
1.
bezel first by unfastening the threaded screws on the
bottom of the case.
Insert the Ethernet module into the front expansion
2.
slot. You should hear a click when the module connects
to the system’s mainboard.
Fasten the screw back on the bottom of the case to
3.
secure the module on the system.
3.5” HDD is installed on the opposite side of
the power supply unit
2.5” HDD is installed on the same side of the
power supply unit
Note:
The Ethernet expansion module occupies the same
space as the 3.5” HDD. So if an Ethernet module is used on
the system, it is only possible to install a 2.5” HDD.