Installing front ethernet module, Chapter 2, Hardware setup – Lanner FW-7575 User Manual

Page 12

Advertising
background image

7

Hardware Setup

Chapter 2

Network Application Platforms

.

3.5” HDD installation

2.5” HDD installation

Installing Front Ethernet Module

To install the front Ethernet module, take off the front

1.

bezel first by unfastening the threaded screws on the

bottom of the case.
Insert the Ethernet module into the front expansion

2.

slot. You should hear a click when the module connects

to the system’s mainboard.
Fasten the screw back on the bottom of the case to

3.

secure the module on the system.

3.5” HDD is installed on the opposite side of
the power supply unit

2.5” HDD is installed on the same side of the
power supply unit

Note:

The Ethernet expansion module occupies the same

space as the 3.5” HDD. So if an Ethernet module is used on
the system, it is only possible to install a 2.5” HDD.

Bottom view of the system

Advertising