2.6

Start-Up Sequence

WARNING:

THERE ARE DANGEROUSLY HIGH VOLTAGES PRESENT WITHIN THE

ENCLOSURE OF THE POWER SUPPLY SYSTEM. CAUTION MUST BE TAKEN

WHEN WORKING WITH THE ENCLOSURE. IT IS RECOMMENDED THAT ALL

WORK BE PERFORMED BY QUALIFIED ELECTRICAL PERSONNEL ONLY.

NOTE: INITIAL START-UP SHOULD BE PERFORMED WITH NO-LOAD ON THE SYSTEM.

1.

Re-install all panels that may have been removed during installation.

2.

Make sure the input circuit breaker is in the off position.

3.

Energize the primary building power.

4.

Turn on the main AC input breaker.

5.

Verify that the output voltage is within the specified range.

6.

Verify output phase rotation is correct.

7.

Turn the system off.

8.

Connect the loads one at a time and repeat Step 5.