Electrical Safety

Prior to opening the housing, disconnect

the Solar Inverter from the electricity of

the grid and the PV generator.

After disconnection from the PV generator

and the grid, there is still lethal voltage

inside the Solar Inverter and at the

PV generator hubs for approximately five

minutes. It takes that long for the energy-

storing capacitors to fully discharge.

After having disconnected the Solar Inver-

ter from the grid and the PV generator,

wait at least five minutes before opening

the Solar Inverter.

Mechanical Safety

During assembly, make sure the cables

or connecting lines attached to the Solar

Inverter are installed safely and suitable

mechanical cable retaining devices (e. g.

cable channels) are used.