5 AL058-01

8. Set the top panel in place on the columns and

secure with M4

10 screws provided. Do not

tighten at this time. (See FIG.8)

12. From the outer side, use M5

10 screws to

fasten the fixing hoop on the right and left support.

Fasten the other side of the fixing hoop after the

cylinder is in place. (See FIG.11)

Note: The installer must supply an external regulator

with a hose (with 5/8” nut at one end, and a regulator

at the other end) and a 20# Vertical Acme with OPD

LP cylinder.

1. Turn the door knob clockwise and open heater

door.

2. Remove dustproof wrap from regulator.

3. Set cylinder flat on base compartment (See FIG.12)

4. Connect regulator with cylinder. Tighten with care.

Do not over-pressurize the valve.

5. Before opening gas supply valve, make sure

control knob is in the OFF position. Open gas

supply valve. Apply a mixture of liquid soap and

water to all joints. Do not use an open flame.

Bubbles forming show a leak. Check all

connections for leaks immediately.

9. Attach the screens to columns with M4

10

screws provided. Do not tighten at this time. (See

FIG.9)

10. Tighten the screws of step 8,9,10 to finish

installation.

11. Attach the handle to the middle base with 2 hex

head screws provided. (See FIG.10)

Figure 8-Top panel installation

Figure 9-Screens installation

Figure 10-Handle installation

Figure 11-The fixing hoop installation

Figure 12-Cylinder set and pipe

installation

CONNECTING TO GAS SUPPLY