3-8 Planning Your System Rack Configuration

Calculating Load and Determining UPS
On-Battery Run Time

When you have chosen your configuration, you can use Table 3-4 and Table 3-5
to determine the load on a single power source and how much run time your
configuration can expect from your UPS in the event your main AC service is
interrupted.

To calculate the load and your on-battery run time, perform the following steps:

1. Determine the total load placed on each power source. The maximum load

you can place on a single power source is:

Source

Maximum Load

UPS

3000VA (2250W)

PDU

2880VA

Table 3-4 provides Volt/Amp load values of system components and
provides space to include other options.

You can calculate Volt/Amps by multiplying a component’s voltage by its
current requirement.

Voltage * Amps = VA

Or if your component’s power requirement is expressed in watts, multiply its
wattage rating by 1.4.

Watts * 1.4 = VA