GE Industrial Solutions EntelliGuard 800–2000 A Frames, 240–600 Vac Maintenance Manual User Manual

Page 24

Advertising
background image

EntelliGuard™ 800–2000 A Power Circuit Breakers
Chapter 5. Breaker Maintenance

14

5. Remove the four bolts, washers, and nuts that attach

the secondary disconnect mounting plate to the

back frame. Remove the mounting plate.

6. Remove one of the snap rings and slide out the pin

connecting each of the movable contact assemblies

to the breaker main shaft, as illustrated in Figure 7.

7. Carefully place the breaker on its back, resting on

the primary disconnects.

8. Remove the six bolts and lock washers attaching the

front and back frames on the side panels.

9. Lift the front frame straight off the back frame.

Reconnection of Front and Back Frames for

EGS08, EGF08, and EGH08

The following procedure is illustrated in Figure 8.

1. Carefully place the back frame on a suitable work

surface, resting on the primary disconnects.

2. Place the front frame assembly onto the back frame,

being careful to line up the mounting holes in the

side panels. Insert the six bolts and lock washers and

tighten them to 200 in-lb.

3. Carefully place the breaker upright, resting on its

bottom surface.

4. Reconnect the movable contact assemblies to the

breaker main shaft by inserting the connecting pin

and reattaching the snap ring, as illustrated in

Figure 7.

5. Place the secondary disconnect mounting plate in

position and secure with the four bolts, washers, and

nuts.

6. Connect the ends of the tie bars to the secondary

disconnect mounting plate and attach the other

ends to the front frame with the bolt, lock washer,

and nut removed earlier. Tighten to 96 in-lb.

7. Place the flexible washer on the molded pin on the

bottom of the secondary disconnect, then slide the

two feet into the slots on the mounting plate. Secure

with the two screws and standoffs, as illustrated in

Figure 6. Replace the wire bundle into the channel

on the top of the frame and secure with wire ties.

8. Insert the four interphase barriers into their mount-

ing slots.

9. Slide the arc chutes into position, with the slots over

the movable contact arms. Secure with the bolts and

lock washers removed on disassembly.

10. Check that no wires are interfering with breaker

operation and that all bolts and nuts are tight.

Operate the breaker a few times to verify proper

operation.

Figure 6. Removing or installing the secondary disconnect.

Figure 7. Movable contact connection to the breaker main shaft on

EGS08, EGF08, and EGH08 breakers.