Powervac, 5kv vertical lift chapter 10. maintenance – GE Industrial Solutions PowerVac 5kV VL PV VL 4.16-250-0 User Manual

Page 33

Advertising
background image

33

Timing may be checked by monitoring control
circuit voltage and using no more than six volts
DC and one ampere through the vacuum inter-
rupter contact to indicate closed or open condi-
tion. Typical time ranges vary with coil volt-
age, but nominal values are:

Initiation of trip signal to contact parting

32-45 milli-seconds

2 milli-seconds maximum pole spread

Initiation of close signal to contact closing

35-75 milli-seconds

2 milli-seconds maximum pole spread.

Trip-free operation may be checked by applying
a simultaneous close and trip signal, and a mini-
mum reclose operation may be checked by trip-
ping a charged breaker open while maintaining
a close signal.

Instantaneous reclose time 85-150 milliseconds.

*Time from application of trip signal until
breaker contacts reclose.

Figure 27. Opening Speed Adjustment

1. Lock Nuts
2. Opening Spring
3. Outer Bell Crank
4. Primary Cross Shaft

PowerVac

®

5kV Vertical Lift

Chapter 10. Maintenance

Figure 26. Sample Operating Speed Graphs

The opening speed is modified by moving the
speed adjusting nuts on the opening spring as-
semblies. A change in the opening speed af-
fects the closing speed Reference Figure 27.

The operating speeds for 5 cycle breakers
with the MOC are as follows:

Operation

Feet Per Second

Open

6.5 normal, 4.5 minimum

Close

2.6 nominal, 4.2 maximum