GE Industrial Solutions Cable Operator Mechanisms for Thermal-Magnetic E150 and Spectra SE150, SF250, and SG600 MCCBs User Manual

General

Advertising
background image

GEH6290

g

Cable Operator Mechanisms for
E150, SE150, SF250, and SG600
Spectra RMS™ Circuit Breakers

Type SCH1/1X, SCH2/2X Flange-Mounted
Handle Assemblies, Cable Series SC3L–SC10L
and Type SC0M1A, SCOM1EF, and SCOM1G
Breaker-Mounted Operating Mechanisms

General

GE Cable Operating Mechanisms are suitable for

application with GE circuit breakers mounted in a wide

variety of flanged enclosure types and sizes.
Flange-mounted handle assemblies are available for

NEMA Type 1, 3R, 12, or 13 enclosures in either 6-inch,

Model SCH1, or 10-inch handle lengths, Model SCH2.

Corresponding assemblies, SCH1X and SCH2X, are

available for NEMA Type 4/4X enclosures. Handle

assemblies are suitable for either left or right flange

operation.
The handle assembly is combined with one of eight

operating cables, with lengths from 3 to 10 feet, to cover a

broad range of breaker mounting locations in the

enclosure. The cable links the handle assembly to the

breaker-mounted operating mechanism and transmits the

mechanical force and motion of the handle mechanism to

the breaker-mounted mechanism. The force and motion

is transmitted independently of the breaker mounting

plane or location relative to the location of the handle

assembly, provided only that the bending radius of the

cable is no less than 3 inches. No mounting reinforcement

of the breaker or enclosure flange is required.
The breaker operating mechanism mounts directly to the

face of the breaker and does not involve any mounting

interface with the enclosure. Standard breaker mounting

screws for tapped holes are furnished with each

mechanism to mount the breaker in the enclosure.
Examine Table 1 to ensure that the handle assembly,

cable, and breaker operating mechanism you have are

correct for the job. Check Table 2 to ensure that the cable

is long enough to reach the breaker and that the 3-inch

minimum bending radius requirement is not violated.
Installation of the handle assembly onto the enclosure

flange can be performed independently from installation

of the breaker operating mechanism onto the circuit

breaker and from installation of the circuit breaker in the

enclosure. Installation of the cable between the handle

assembly and the breaker mechanism should be the final

step. The breaker operating mechanism is to be installed

onto the circuit breaker after the breaker has been

mounted in the enclosure.

Table 1. Mechanism Selection Guide


Circuit Breaker

Handle Operating Mechanism Cat. No.

Breaker Operating

Mechanism


Operating Cable

Cable Operator

Mechanism

Installation

Type

NEMA 1, 3R, 12, 13

NEMA 4/4X

Cat. No.

Cat. No. Series Instruction

E150

SCOM1A

SE150 SCH1 SCH1X

SC0M1EF

SC3L–

GEH-6290

SF250 SCH2 SCH2X

SC10L

SG600

SCOM1G

SK1200 SCH2K SCH2KX SCOM1K

SC3H–SC10H

GEH-6291