Table 2. Circuit Breaker Mounting-Zone Dimensions

To determine maximum mounting dimensions for 60-

inch through 120-inch-long operating cables, add the

respective additional lengths to the 48-inch cable

maximum dimensions. (For example, add 12 inches to E,

F, and G dimensions for 60-inch cable length.)

Maximum Dimensions in Inches

Enclosure

36” Cable

48” Cable

Depth

E* F G E* F G

8 13.5

4.0

15.0

25.5 16.0 27.0

10 13.0

5.0

14.8

25.0 17.0 26.8

12 12.8

6.0

14.5

24.8 17.0 26.5

16 10.5

4.5

14.2

22.5 16.5 26.2

18 8.5

3.5

12.6

20.5 15.5 24.6

20

— 0.5 10.0 22.0 15.0 24.0

24

— — —

19.5

14.0

22.0

* Maximum E dimension only if F = 4.5”.

When cable is installed, the minimum cable bend radius

should not be less than 3 inches. The minimum cable

bending requirement must be met to ensure a safe

operating environment.

Table 3. Circuit Breaker Mounting Dimension

Breaker Type

A

B

C

D

Tap Size

E150 1.38

4.88

0.72 6.31 8-32

SE150 1.38

4.88

0.72 6.51 10-32

SF250

1.38 7.75 1.19 10.12 12-24

SG600 1.81

7.75

1.19 13.62 12-24

Figure 1. End view of flange and cover (right end shown).

Table 4. Handle Dimensions (see Figure 3)

NEMA 12

Handle Cat. No.

NEMA 4/4X

Handle Cat. No.

L

H

SCH1 SCH1X

6.04

2.38

SCH2, SCH2K

SCH2X, SCH2KX

9.38

3.00

Figure 2. Flange details.