Off Line Equalization Panel and Converter for GPS4848/GPS4812

4 - 2 Converter Installation

Issue 4 January 2008

Installation Guidelines and Procedures, continued

Installation

Sequence

Installing the ES671 Converter

Step

Action

1

Ensure that the front panel switch on the converter is in
the Standby position.

2

Set the time interval switch to the desired position

(12/24 hours). See Figure 4-1.

3

Set the current limit switch to the desired position. See
Figure 4-1.

CURRENT

LIMIT

EQUALIZE

TIME

66A

100A

12HR

24HR

Figure 4-1: Switch Positions on the ES671 Converter

Continued on next page.