Off Line Equalization Panel and Converter for GPS4848/GPS4812
4 - 2 Converter Installation
Issue 4 January 2008
Installation Guidelines and Procedures, continued
Installation
Sequence
Installing the ES671 Converter
Step
Action
1
Ensure that the front panel switch on the converter is in
the Standby position.
2
Set the time interval switch to the desired position
(12/24 hours). See Figure 4-1.
3
Set the current limit switch to the desired position. See
Figure 4-1.
CURRENT
LIMIT
EQUALIZE
TIME
66A
100A
12HR
24HR
Figure 4-1: Switch Positions on the ES671 Converter
Continued on next page.