RQ Series Startup Form

Job Name:_______________________________________________

Date:______________

Address:______________________________________________________________________

______________________________________________________________________________

Model Number:_________________________________________________________________

Serial Number:_____________________________________________ Tag:_______________

Startup Contractor:______________________________________________________________

Address:______________________________________________________________________

_______________________________________________________

Phone:______________

Pre Startup Checklist

Installing contractor should verify the following items.

1. Is there any visible shipping damage?

Yes No

2. Is the unit level?

Yes No

3. Are the unit clearances adequate for service and operation?

Yes No

4. Do all access doors open freely and are the handles operational?

Yes No

5. Have all electrical connections been tested for tightness?

Yes No

6. Does the electrical service correspond to the unit nameplate?

Yes No

7. On 208/230V units, has transformer tap been checked?

Yes No

8. Has overcurrent protection been installed to match the unit nameplate

requirement?

Yes No

9. Have all set screws on the fans been tightened?

Yes No

10. Do all fans rotate freely?

Yes No

11. Does any field water piping to the unit appear to be correct per design

parameters?

Yes No

12. Is all copper tubing isolated so that it does not rub?

Yes No

13. Has outside air rain hood been opened?

Yes No

14. Have the damper assemblies been inspected?

Yes No


15. Are air filters installed with proper orientation?

Yes No

16. Have condensate drain and p-trap been connected?

Yes No

Ambient Temperature

Ambient Dry Bulb Temperature ________°F

Ambient Wet Bulb Temperature ________°F