Vf series, General pump – General Pump VF Owner Manual User Manual

Page 13

Advertising
background image

GENERAL PUMP

A member of the Interpump Group

VF SERIES

In case the pump has not run for a long period

of time, verify the correct operation of the

suction and delivery valves.

10.2 Start-up

1. When starting the pump for the first time, check for

the correct direction of rotation.

2. The pump must be started off-load.

3. Verify correct feeding pressure.

4. During operation check that the rotating speed does

not exceed the rated value.

5. Before putting the pump under pressure let it run for

at least 3 minutes.

6. Before stopping the pump, release the pressure by

acting on the adjustment valve or on any discharging

device, and reduce RPM (diesel applications).

10.3 Seal Packing Cooling Circuit

During operation, a certain amount of water coming from

the seal packing cooling circuit is discharged from orifice

4 (see fig. 15). The draining of this circuit must be sent

back to the suction line before the booster pump (fig. 15),

or in an appropriate tank.

11. PREVENTIVE MAINTENANCE

To guarantee pump reliability and efficiency, respect the

maintenance intervals as indicated in the table in fig. 16.

PREVENTIVE MAINTENANCE

EVERY 500 HOURS

EVERY 1000 HOURS

Check oil level

Change oil

Check / Replace:

• Valves

• Valve seats

• Valve springs

Check / Replace:

• H.P packings

• L.P. packings

12. STOPPING THE PUMP FOR LONG PERIODS

12.1 Inactivity for Long Periods

If the pump is started up for the first time after a

long period from the shipment date, before start-

ing operation check the oil level, check the

valves as indicated in Chapter 10, and therefore

follow the start-up procedures described.

12.2 Filling the Pump With an Anti-Corrosion

Emulsion or Anti-freeze Solution by Using an External

Diaphragm Pump as in the Layout Shown in

Paragraph 9.6, fig. 6

a) Close the filter drain, if open.

b) Be sure that the connecting pipe is clean, spread with

grease and connect it to the high pressure outlet port.

c) Fasten the suction hose to the diaphragm pump.

Open the pump suction and fit hose between it and

the diaphragm pump.

d) Fill the container with the solution/emulsion.

e) Put the free extremities of the suction hose and the

high pressure outlet hose inside the container.

f) Start up the diaphragm pump

g) Pump the emulsion until it comes out of the high

pressure outlet hose.

h) Continue pumping for at least another minute; if

needed, the emulsion can re reinforced by adding for

example Shell Donax.

i) Stop the pump, remove the hose from the suction

connection and close it with a plug.

j) Remove the hose from the high pressure outlet port.

Clean, grease and plug both connections and the

hoses.

12.3 Hoses

a) Before greasing and protecting the hoses according to

their previously described procedure, dry the connec-

tions using compressed air.

b) Cover with polyethylene.

c) Do not wrap them too tightly; be sure there is no

folding.

Page 13

Ref 300662 Rev.C

06-12