Maintenance, 1 daily check, 2 daily check and maintenance procedures – Yokogawa IR200 User Manual

Page 70

Advertising
background image

7 - 1

IM 11G02M01-01E

7. MAINTENANCE

7.1 Daily check

(1) Zero calibration and span calibration

1.

It is used for zero point adjustment. For calibration, refer to 6.9.1, Zero calibration.

2.

After zero calibration, perform span calibration. For calibration, refer to 6.9.2, Span calibra-
tion.

3.

Zero calibration and span calibration should be performed once a week, if required.

(2) Flow check

1.

Sampling gas flow rate and purge gas flow rate should be as follows;

Sampling gas flow rate: 1.0

±

0.5L/min (stable)

Purge gas flow rate:

About 1L/min

2.

Maintenance and check should be carried out every day, if required.

7.2 Daily check and maintenance procedures

Table 7-1 Maintenance and check list

Dust is mixed in the
sample cell.

Standard flow rate is
1L/min. It is not within
the range of the
specified flow rate of
0.5 to 1.5 L/min.

Much clogged

Out of zero point

Out of the span
point

Irrespective of
phenomena

Irrespective of
phenomena

Lower indication

Replacement of Monitor
filter (membrane filter)

Zero point of gas
analyzer

Span point of gas
analyzer

Replacement of monitor
filter (membrane filter)

Every week

Every day

Every year

Gas analyzer

Recorder indication

Air is sucked in
anywhere in the
sampling tube.

Primary filter is
damaged.

Overhaul.

Replace filter (paper).

Span calibration

Zero calibration

Adjust the flow rate with
flow rater needle valve.

Replace primary filter.
Replace filter
(filter paper).

Check for leak of
the sampling line
and repair, if required.

Clean sampling cell
and check for
sampling device,
especially gas filter.

Remedy

Cause

Phenomena

Parts to be checked

Check for purge gas
flow if purging the
sampling gas flow
instrument.