Inspection on Arrival

1. Inspect unit on delivery.
2. Report any damage to the delivery carrier.
3. Request a written inspection report from the

Claims Inspector to substantiate claim.

4. File claims with the delivery carrier.
5. Compare unit received with description of

product ordered.

6. Report incomplete shipments to the delivery

carrier and your Donaldson representative.

7. Remove crates and shipping straps. Remove

loose components and accessory packages
before lifting unit from truck.

Installation Codes and Procedures

Caution!

OSHA may have requirements regarding
recirculating filtered air in your facility.
Consult with the appropriate local
authorities to ensure compliance with all
codes regarding recirculating filtered air.

1. Safe and efficient operation of the unit depends

on proper installation.

2. Authorities with jurisdiction should be

consulted before installing to verify local codes
and installation procedures. In the absence of
such codes, install unit according to the
National Electric Code, NFPA No. 70-latest
edition.

3. A qualified installation and service agent must

complete installation and service of this
equipment.

Installation

Site Selection, Grade-Mounted Units

1. The unit can be located on a reinforced

concrete foundation or rooftop.

2. Wind, seismic zone, and other live-load

conditions must be considered when selecting
the location for rooftop-mounted units.

3. Provide clearance from heat sources and

interference with utilities when selecting the
location for suspended units.

4. Portable units require no special installation

accommodations.

Unit Location

1. When hazardous conditions or materials are

present, consult with local authorities for the
proper location of the collector.

2. Foundation or roof support must be capable of

supporting the entire weight of the unit, plus the
weight of the collected material, piping, and
ductwork.

3. Prepare the foundation in the selected location.

Install anchor bolts to extend a minimum of
1 3/4-inches above foundation.

4. Locate the collector to ensure the shortest and

straightest inlet- and outlet-duct length, easy
access to electrical and compressed-air
connections, and routine maintenance.