Installation

18

ESP Primer System Instruction Guide

p/n: 029-0810-01-0

Attach the ground strap from the truck chassis to the priming pump ter-
minal stud to ensure a ground for the motor. See appropriate drawing,
sheet 2.

The ground strap is appropriately sized for a 12 or 24 volt DC, 300 or 150
amp load.

To prevent damage to the solenoid plastic housing, when installing or
removing wire leads, DO NOT apply side loads to the nuts. (See Figure
3-1: “Solenoid Connector Arrangement.”)

Figure 3-1: Solenoid Connector Arrangement

When using a terminal lug on the battery connection with a 5/16” (8 MM.)
diameter hole, the lower washer is not needed.

If the hole is larger than 5/16”, washers are required both above and
below the terminal. Torque to 50 - 60 in. lbs. (6 - 7 N-m) maximum.

DO NOT overtighten to avoid stripping the stud from plastic cap.

The solenoid-to-ground terminal, 10-32 UNC, is factory connected and
torqued to 15 - 20 in. lbs. (1.7 - 2 N-m).

DO NOT overtighten to avoid stripping the stud from plastic cap.

For complete electrical installation instructions, see sheet 2 of drawing
“12 Volt ESP System” on page 54 or see sheet 2 of drawing “24 Volt ESP
System” on page 54.