- 15 -

shaft with the hole goes toward the front right
side of the machine with the breather/cover (#18).

11. Install the idler shaft covers (#7 on the pulley side,

and (#18 on the hydraulic side). Secure each cover
with four hex head flange screws (#23) using
LOCTITE #243 on the bolt threads and torque the
flange screws to 13 ft.-lbs. See the figure #3 for
LOCTITE #515 gasket maker application. Check
idler shaft for minimum of .020” end play after
covers are installed and the bolts are torqued
.

12. Install the 90 degree fitting (#2) containing the roll pin

(#20) into the bearing cover (#18) using LOCTITE
#565 sealant on the threads. Make sure the port for
the breather faces the top of the baseplate
housing.

13. Install the breather (#3) into the 90 (#2) degree fitting.

14. Install the exciter weights (#17) on the idler shaft (#8)

and secure with four socket head cap screws (#24)
using LOCTITE #243 thread locker sealant and
torque the cap screws to 32 ft.-lbs.

15. Press one bearing inner race onto one end of the

input shaft (#16). Note: Make sure the bearings
and their inner races are kept as a matched set.
The flange on the inner race goes toward the
shoulder of the shaft.

16. Install the input gear (#10) onto the input shaft (#16)

and slide to the end with the bearing inner race.

17. Press the other bearing inner race onto the input

shaft (#16).

18. Install the input shaft subassembly into the baseplate

with the keyed end toward the left side (pulley side) of
the base plate.

19. Install the pulley side shaft cover (#9), containing the

shaft seal (#5) over the input shaft on the pulley side

of the baseplate. See the figure #3 for LOCTITE
#515 gasket maker application.
Lubricate the
input shaft seal and bearing with exciter oil
before inserting the input shaft through the oil
seal in the cover to prevent tearing the seal.

20. Secure the input shaft cover with the four flange head

crews (#23) using LOCTITE #243 thread locker
sealant on the bolt threads and torque the capscrews
to 13 ft.-lbs.

Refer to LOWER SHAFT ASSEMBLY, page 30.

21. Install the other input shaft cover (#12) and secure

with the four flange head screws (#22) using
LOCTITE #243 thread locker sealant and torque the
screws to 13 ft.-lbs. See the figure #3 for LOCTITE
#515 gasket maker application. Check input shaft
for minimum of .020” end play after covers are
installed and the bolts are torqued.

22. Install one exciter weight (#17) to the input shaft on

the hydraulic housing side of the baseplate with two
socket head cap screws (#24) using LOCTITE #243
thread locker sealant and torque the cap screws to 30
ft.-lbs. Be careful to use a small amount of thread
locker to avoid dripping it into the helix pin carrier
bearings at installation.

23. Slide the input gear (#10) toward the pulley side of

the input shaft (#16). The gears should not be
meshing at this time.

Refer to LOWER SHAFT ASSEMBLY, page 30.

24. Install the ball bearings (#3) and the spacer washer

(#7) onto the shift shaft (#10) and secure with the e-
clip (#5).

25. Press the shift shaft and ball bearing assembly into

the helix pin carrier (#9) and secure with the internal
retaining ring (#8).

BASEPLATE GEAR TIMING

TIMING MARK LOCATION

HUB OF IDLER GEAR
OPPOSITE SHAFT
SHOULDER

EXCITER WEIGHTS
ROTATED AS SHOWN

HELIX PIN ORIENTED
HORIZONTALLY

HYDRAULIC HOUSING
SIDE OF BASEPLATE

FIGURE 5

Advertising
This manual is related to the following products: